Sheet Pile Installation in Ciliwung River Touched 81 Percent
access_time December 15 2015 03:49 PM remove_red_eye 1621
Reported by Nurito | Translated by Trias Risangayu
Reported by Nurito | Translated by Trias Risangayu
The installation of 2 km sheet pile along Ciliwung riverbank starting from Tongtek Bukit Duri bridge up to Jl KH Abdullah Syafii bridge Kampung Melayu has reached 81 percent. The remaining work will be done this month.
The project has reached 81 percent and the remaining project must be done this month
Teuku Iskandar, Ciliwung-Cisadane Flood Control Office (BBWSCC), explained flood will not hit Kampung Pulo if the sheet pile is already installed fully. In fact, the flood will hit Bukit Duri, Tebet, South Jakarta since the normalisation is not run yet.
Kodam Jaya's Troopers Cleaned Up Trash on Ciliwung River“The project has reached 81 percent and the remaining project must be done this month,” said Iskandar, Monday (12/14).
He added that his side will create four water pol
der to accommodate water and anticipate flood. Each polder will get 1,000-2,000 later per second water pump.“Those pumps will be used to suck water if Kampung Pulo is flooded,” he closed.