Pemasangan Sheetpile Ciliwung Capai 81 Persen

Sheet Pile Installation in Ciliwung River Touched 81 Percent

The installation of 2 km sheet pile along Ciliwung riverbank starting from Tongtek Bukit Duri bridge up to Jl KH Abdullah Syafii bridge Kampung Melayu has reached 81 percent. The remaining work will be done this month.

The project has reached 81 percent and the remaining project must be done this month

Teuku Iskandar, Ciliwung-Cisadane Flood Control Office (BBWSCC), explained flood will not hit Kampung Pulo if the sheet pile is already installed fully. In fact, the flood will hit Bukit Duri, Tebet, South Jakarta since the normalisation is not run yet.

Kodam Jaya's Troopers Cleaned Up Trash on Ciliwung River

“The project has reached 81 percent and the remaining project must be done this month,” said Iskandar, Monday (12/14).

He added that his side will create four water polder to accommodate water and anticipate flood. Each polder will get 1,000-2,000 later per second water pump.

“Those pumps will be used to suck water if Kampung Pulo is flooded,” he closed.

Linked News
Popular News indeks
  1. Transjakarta Modifies Mikrotrans Routes JAK 48A, JAK 50, and JAK 79

    access_time12-10-2026 remove_red_eye540 personAldi Geri Lumban Tobing
  2. Way to Go, Kid! Transjakarta Surprises Young Local Commuter in East Jakarta

    access_time11-10-2026 remove_red_eye464 personAldi Geri Lumban Tobing
  3. Dengue Cases Decline in Jakarta as Prevention Efforts Intensify

    access_time16-10-2026 remove_red_eye398 personAldi Geri Lumban Tobing
  4. Jakarta Sends Transport Personnel to Street Level to Clear Morning Rush-Hour Jams

    access_time11-10-2026 remove_red_eye385 personAldi Geri Lumban Tobing
  5. CiLung Festival Lets Visitors Ride Boats Made from Recycled Plastic Bottles

    access_time16-10-2026 remove_red_eye384 personAldi Geri Lumban Tobing